London Fire Brigade

Public notice details

[use back button to return to summary]

Enforcement Notice details

Address to which notice applies:
Hazelwood Tower, Golborne Gardens, London, W10 5DT

Borough premises situated in: Kensington and Chelsea

Property type: Purpose Built Flats>=4 floors

Date of notice: 18/01/16

Notice type: Enforcement Notice

Name and address on whom notice was served:
The Royal Borough of Kensington & Chelsea Tenant Management Organisation Limited, 292a Kensal Road, London, W10 5BE,

Responsibility of person on whom notice served: Other person having control

Applicable legislation: Article 30: Regulatory Reform (Fire Safety) Order 2005

Date of expiry of notice/Compliance due date: 18/07/16

Date remedial works completed: 15/11/16

Additional information:

Time limit for completion of works extended to 18 October 2016
(Date: 15/06/16)


Schedule

Article Details of failure to comply with order Necessary steps to comply with order

Article 9

Failure to review the fire risk assessment.

Implement regular program to review fire risk assessment.

Article 10

Failure to apply the principles of prevention to the implementation of the preventative and protective measures identified by the risk assessment.

Implement preventative and protective measures identified in fire risk assessment, on the basis of the principles of prevention.

Article 11

Failure in the effective management of the preventive and protective measures.

Implement arrangement for the effective planning, organisation, control, monitoring and review of the preventive and protective measures.

Article 14

Failure to provide and/or maintain adequate and clearly indicated emergency routes and exits that lead to a place of safety.

Ensure that adequate escape routes and exits leading to a place of safety are provided and that these are maintained clear and available for use at all times that the premises is occupied.

Article 15

Failure to establish an appropriate emergency plan.

Prepare/update emergency plan.

Article 17

Failure to ensure that the premises and any facilities, equipment and devices are maintained in an efficient state, in effective working order and in good repair.

Ensure that adequate maintenance systems are in place to ensure that the premises and any facilities, equipment and devices are maintained in an efficient state, in effective working order and in good repair.